What inspections might I need for my project?

A SUMMARY OF INSPECTIONS GROUPED 1 THROUGH 5

The plan review will determine which inspections are required for your project:

1ST Inspection

  1. Appropriate erosion control
  2. Foundation location pursuant to setbacks
  3. Temporary power for approval
  4. Compaction of excavated area
  5. Foundation substrate & footing forms per R403
  6. port-o-let on site

2nd Inspection

  1. Anchor bolts (straps not permitted)
  2. All snap tie ends removed interior/exterior
  3. Perimeter drain extended 35’ from foundation
  4. Temporary power for approval
  5. Sleeve for soil pipe (2) pipe sizes larger
  6. Sleeve for water line (2) pipe sizes larger
  7. Stone for perimeter drain
  8. Filter fabric in place
  9. Water stop at snap ties ends
  10. Moisture proof/water proof foundation
  11. Foundation test for re-bar if code required
  12. Erosion control maintained
  13. Ground to re-bar (Ufer Ground)

3rd Inspection

  1. Rough frame
  2. rough electrical
  3. Rough plumbing
  4. No corner boards, siding or building wrap applied
  5. Roofing per manufacturers installation
  6. U 0.35 or less windows installed with flexible flashing (spec stickers left on)
  7. Doors installed with flexible flashing
  8. Fire safing/stopping
  9. Chimneys and vents
  10. Erosion control maintained

4th Inspection

  1. Insulation installed per IECC
  2. Permanent power approval
  3. Erosion control maintained

5th/ Final Inspection

  1. Electrical panel, with panel front removed, by electrician
  2. Circuit directory typed and secured inside of panel door
  3. Final electrical
  4. Energy Code Compliance Certificate secured inside of Service Entrance panel door
  5. Finish grade sloped 6: in 10’ from foundation and finish grade 6” from  wood siding, sheathing, and wall framing
  6. Wellhead inspection well report, standard analysis, DES, fact sheet WD-WSEB-2-1
  7. Garage/ Unit  fire separation
  8. Decks
  9. Siding installed per manufacturers guidelines
  10. Homeowners manuals on maintaining their septic system, as well as those  provided with appliances and products
  11. Interior stairs, rails and safety glass
  12. Stairs exterior with concrete stair rest at base
  13. Property number
  14. Escape window to grade checked
  15. Impact fee paid by certified bank check
  16. Fire Department sign off on boiler
  17. Fire Department sign off on smoke detectors
  18. Public Works director sign off on driveway
  19. Water Department sign off for Town water
  20. Sewer Department sign off for Town sewer
  21. Exterior lighting shaded to property line
  22. Erosion control maintained – leach field loamed and seeded
  23. Septic permit to operate