Planning Board Site Plan Approval Process |
|
|
|
SITE PLAN APPROVAL PROCESS
Planning Board meets once a month
Optional Submissions: Preliminary Conceptual Consultation-No Public Notice
Design Review-Public Notice
Site Plan Submissions-Public notice required Minor Review Major Review
\ /
15 days Staff Review
|
Site Plan Review Planning Board Review
1.Application Acceptance
2. Applicant Presentation
3. Public Hearing
4. Deliberation
5. Decision *
*Same meeting or future meetings not to exceed 90 days
|
A. Approval
B. Approval with conditions
C. Disapproval
|